Household Waste Recycling Centre Refurbishment
The works were undertaken on a live house hold waste recycling centre which was required to be open to the public whilst the works were undertaken
Works comprised:-
• New of a 40m long 5m high pedestrian canopy complete with lighting.
• New steel gantries after openings had been fabricated in the existing sheet pile wall.
• Installation of an oil store and bike shed
• Formation of a car park and concrete hardstanding for skip storage
• Provision of a meet and greet kiosk together with power supply.
• Relocation of existing CCTV and lighting columns around the site.
• Installation of a weighbridge together with the concrete foundations.
FCC Area Manager commented “DXI have yet again delivered a first class project whilst undertaking to work alongside the general public and adhere to the very tight programme”
CLIENT
FCC Environment Ltd
REFERENCE CONTACT
Delvis Firth
CONTRACT VALUE
£247K
CONTRACT DETAILS
Refurbishment of an active HWRC site including installation of pedestrian canopy, gantries, car parks & attenuation tank