Reinforced concrete slabs
Re-location of the existing compost pods to a temporary constructed HDPE lined composting pad.
Blasting of 22,000m3 of rock on three faces within a redundant quarry and processing (crushing & screening) into primary graded aggregates for incorporation into site batched structural concrete.
Trimming, including scarification of rock floor prior to regulating with fines material in preparation for sub-base formation.
Placement and compaction of a 200mm thick layer of Type 1 across the footprint of the proposed composting pad, prior to placement of a 200mm thick layer of site batched roller compacted concrete over 9480m2.
Construction of 210 lm of cast in-situ concrete lined channel, laid to falls and connected to a HDPE lined lagoon.
Stringent materials testing including flexural concrete beam tests were undertaken to satisfy the requirements the Environment Agency.
The lagoon was enclosed with a 2.4m high palisade fence.
All unsuitable material, including incompetent rock, soils from two fault lines and fines was spread and levelled within existing quarried areas.
CLIENT
FCC Environment Ltd / Veolia
REFERENCE CONTACT
WSP / QualSurv Project Services / FCC Environment
CONTRACT VALUE
£2.53Million (cumulative)
CONTRACT DETAILS
Stadium seat terracing, Sweeper bays, Wheel wash pits, Push walls